fredag den 30. november 2007

In November the main equipment including two jack-ups (Aarsleff III and Aarselff V), cranes, earthmoving- and piling- equipment, 288 pipe piles for the jetty, pipe piles and sheet piles for the 400 meter combi walls and sheet piles for some 215 meter retaining walls departed by special cargo vessel, the Da Fu of Panama (Big Lift), from Denmark and the Netherlands.