onsdag den 9. december 2009

Picture of the arrival of the Oasis of the Seas, mooring on the 9th of December 2009 at 07.00 a.m. at the new Jetty in St maarten.


Picture taken by A. Verhaag

mandag den 27. april 2009


The project was completed today, April 27th, 2009, a few weeks after the initial completion date.

See http://www.bnpa.eu/ for more



fredag den 31. oktober 2008

When the cruise jetty was complete by some 60%, hurricane Omar hit the Island in mid October 2008 without any warning from the South American coast. It severely damaged the Cruise jetty structure, sending beams and slabs to the sea-bottom and causing damage beyond repair, resulting in a delay to the construction works of some 3.5 months. (ref. BNPA.eu)

The photo is taken by BNPA.eu

torsdag den 3. juli 2008

Aerial Shot of the Sint Maarten Project Sites

The BNPA main worksite and offices can be seen in the upper right corner, the new cruise jetty on construction is seen in the center of the picture, the new cargo harbour is seen to the right and the new breakwater is seen in the lower right corner.

Please click on the picture to enlarge it (or viewed in Flickr)

mandag den 30. juni 2008

onsdag den 11. juni 2008

Working with both jack-ups at the Cruise Jetty.

The jack-up barge in the background is piling the jetty for the cruise liners. The jack-up barge in the foreground is placing the 40 ton concrete beams for the top slab, where all the guests can disembark the liners and walk to shore. The dredger is seen in background and the sheet pile and anchoring works can be seen in the foreground.

Please click on the picture to enlarge it

mandag den 9. juni 2008

Sandfill at the new Cargo Harbour. In the background, boulders are being from St. Kitts are unloaded, for later use in the new breakwater.